Skip to content
Tilt Up Wall Cutting in Tijuana: Opening a Plant Without Stopping It
  1. Home
  2. Tilt Up Wall Cutting in Tijuana: Opening a Plant Without Stopping It

Tilt Up Wall Cutting in Tijuana: Opening a Plant Without Stopping It

In a Tijuana plant, an hour of downtime costs more than the entire cut. That is why it is planned first.

This guide is for anyone about to hire and wanting to understand what they are buying. If you are after the technical detail of the service, it is on the page for tilt up wall cutting.

Before touching the panel

You need to know whether the panel is load-bearing, where the connectors to the structural frame are, how it is reinforced and which services cross it. A new opening almost always needs a reinforcing frame, and that frame is defined by the structural engineer, not by the cutting crew.

How long it really takes

A typical dock opening is cut and removed in one working day if there is outside access for lifting equipment. Without that access, the time doubles because the panel has to be broken into manageable blocks.

How operations are protected

Poly barriers, cutting-water capture, vacuum extraction on the inside and cordoning of the area. In controlled-environment plants the area is sealed and worked under negative pressure.

The most common mistake

Opening first and sorting the reinforcement afterwards. When the frame arrives late, the panel spends weeks working with an unconfined opening, and that does leave permanent cracking.

Tilt Up Wall Cutting
Clear on what you need? Request a quote and we will reply with method, schedule and price.
GPC Construcciones crew on site

Do you have concrete to cut?

Tell us what needs opening, drilling or demolishing. We reply with method, schedule and a clear price.